Delivery of the fast-tracked Kangaroo Point Green Bridge is about to get underway, with hundreds of local workers to get started on piecing together the longest inner-city active travel bridge in any Australian capital city.
Lord Mayor Adrian Schrinner said residents would soon see establishment of the work sites in the CBD and at Kangaroo Point, with barges to arrive and marine piling to start in early 2022.
“This bridge is going to a major engineering and construction feat for our city and involve innovative techniques that have never been used in Brisbane before,” Cr Schrinner said.
“The construction of this green bridge will involve the best and most advanced construction techniques to ensure river access is maintained while 33 piles are installed, and the 182-metre bridge span connected.
“The Kangaroo Point Green Bridge will be the tallest bridge in Brisbane with its mast 95-metres above the Brisbane River, and we will use a combination of a 72-metre tower crane and barges to install the main pylon before installing the bridge deck spans across the river.
“This bridge is about providing better and safer active travel connections, but it’s also going to be a fantastic landmark for the 2032 Olympics and Paralympic Games.
“The combination of its striking design, boutique bar and restaurant and the critical connection from the heart of the CBD across to the main Olympic Stadium will make it incomparable to anything else in the world.
“I have no doubt it will quickly become one of the most photographed structures in Brisbane.”
Transport Civic Cabinet Chair Councillor Ryan Murphy said the Kangaroo Point Green Bridge would be city changing
“The Schrinner Council said we would fast-track this green bridge and the fact that we’re about to start early works is another milestone met,” Cr Murphy said.
“The construction plan and animation will let residents know exactly how this bridge will be built and what they can expect to see happening.
“The innovative approach to construction will use three major deck lifts to install the main spans, allowing safe access to the river to be maintained.
“This bridge will be built locally by a team of more than 300 contractors and more than 90 per cent of supplies will be sourced from South East Queensland businesses.
“We’ve come a long way in the just over two years since the Lord Mayor first announced the Green Bridges program and we are now getting ready to build this landmark bridge.”
Completion of the Kangaroo Point Green Bridge is expected in late 2023.
CONSTRUCTION FACTS AND FIGURES:
- Number of piles = 33
- Number of land piers = 2
- Number of marine piers = 5
- 8 spans
- Main Span = 182.7metres
- Mast Height is 83m above the deck level, making it the tallest Bridge within Brisbane at 95 metres above the Brisbane River
- Number of tensioned cables = 32
- Total bridge length = 458metres
Nice bridge,Brisbane is growing rapidly I was surprised when I came in early 2020 to Brisbane ,this city has changed alot and more to come,I think 2023 is a golden year for Brisbane
The green bridges are fabulous. Brisbane is a beautiful and vibrant city with great weather that encourages an outdoor lifestyle. Sadly the new flight paths have introduced an ever present roar over the riverside suburbs that severely detracts from the city’s appeal. Hopefully the BCC is working with the federal government to address this issue.
A very nice bridge with a great design. It will also look good at night time lit up. I think that end of the city will become alot more busier. A much needed crossing instead of having to walk around the long way.